Boosteroid, Gaw Capital and Firebird AI plan 480 MW of data centres in Kazakhstan's Data Center Valley
Boosteroid, Gaw Capital Partners and Firebird AI signed preliminary agreements to develop 480 MW of data center capacity in Kazakhstan, according to Data Center Dynamics. The project forms the second phase of Data Center Valley in the Pavlodar region and could expand to 620 MW. The plans were presented at a meeting between Prime Minister Olzhas Bektenov and Deputy Prime Minister and AI minister Zhaslan Madiyev.
The Data Center Valley project calls for up to 1 GW of capacity by 2029. Its first phase includes three data centers with combined capacity of 304 MW, comprising facilities rated at 68 MW, 164 MW and 72 MW.
Construction has moved to foundations and infrastructure at the 68 MW site, which is scheduled to open in the second quarter of 2027. Excavation for the 164 MW Firebird AI facility is 70 percent complete, with opening planned for the third quarter of 2027. The 72 MW facility is due to begin operations in the fourth quarter of 2027.
We hope you enjoyed this article
Consider subscribing to one of our newsletters like AI Policy Brief, Silicon Brief or Daily AI Brief.
Also, consider following us on social media:
More from Regulation
Nov 10 Leaked EU Digital Fairness Act draft would make paid AI shopping agents ask consumers again before buying Nov 10 Irish parliament's AI committee calls for independent testing of high-risk AI and default-off recommendations for children Nov 10 French AI council urges immediate, stricter rules for AI assistants like ChatGPT, Gemini and Grok Nov 10 House Democrats ask Commerce to halt advanced AI chip exports to China over reported intelligence ties to Nvidia's CEO Nov 10 EU consults on DSA election guidelines that would have platforms label deepfakes and test recommender systems before votesMore from Data Centers
Nov 10 Fluidstack starts building its $1 billion-plus Solis Arx AI data centre campus in Virginia Nov 10 TSMC board approves up to $500 million each in Anthropic's IPO and OpenAI Nov 10 Deutsche Telekom expands its Munich AI factory by 20 MW with Nvidia B300 GPUs after the first phase sold out Nov 10 Study links new AI-era data centres to delayed coal plant retirement and 1.96 gigatons of extra CO2 Nov 10 Q.ANT and IONOS open a pilot for running AI models on photonic processors in a German cloudAI Policy Brief
Weekly report on AI regulations, safety standards, government policies, and compliance requirements worldwide.
Industry analysis
2025 Global Business Services Agenda: Gen AI Takes Center Stage
This industry analysis by The Hackett Group explores the transformative impact of generative artificial intelligence (Gen AI) on global business services (GBS) in 2025. The study highlights the shift from exploration to acceleration of Gen AI initiatives, with 89% of executives advancing these projects to improve customer satisfaction, innovate products, and reduce costs. The report also discusses the challenges and strategies for successful Gen AI adoption, emphasizing the need for a technology-enabled operating model and the importance of reskilling the workforce.
Read moreYou may also like
SpaceX AI Plans 6 GW Arizona Data Center Campus
SC Capital and NeoAI Cloud Partner on South Korea AI Data Center
Kazakhtelecom Plans More Than 2,000 New GPUs in 2027
Drax and Brookfield plan AI data center worth over £20 billion
LG CNS leases all capacity at Jakarta AI data center
Daily AI Brief: the AI news that matters, in your inbox.