Norway plans licensing for data centres as grid requests outstrip supply
The Norwegian government will introduce a licensing regime for data centres, covering both existing and new sites, to slow a build-out that now asks for more power than the country can supply, it announced. Grid operator Statnett has paused new grid capacity reservations for data centres until 1 August 2027 at the latest. Existing connections are not affected.
According to Statnett, 800 MW of data centres are already connected, 4,200 MW have reserved capacity and 9,100 MW sit in the queue, with requests for another 18,000 MW. Norway's peak electricity demand is just over 25,000 MW. Energy Minister Terje Aasland said data centres made up 75% of this year's connection requests, Cyprus Mail reports.
The government says data centres are needed for the safe development and use of AI. Licence conditions will weigh digital security and the availability of AI computing capacity in Norway, the Nordic region and Europe. Crypto mining will not count as beneficial to society. Digitalisation minister Torgeir Micaelsen said global cloud companies will face limits on land and power, while sites serving defence, police, health and other critical services get priority, Brussels Signal reports.
Large new users may have to pay more of the grid costs and help build their own power, such as offshore wind or gas plants with carbon capture. The government will also look at state ownership in key projects and plans to present the main principles of the licensing regime in autumn 2027.
We hope you enjoyed this article
Consider subscribing to one of our newsletters like AI Policy Brief, Silicon Brief or Daily AI Brief.
Also, consider following us on social media:
More from Regulation
Nov 13 Senate advances permitting bill that would speed energy projects for data centers Nov 12 Congress leaders back tighter AI chip export curbs after Nvidia scandal Nov 12 South Australia backs gas power for AI data centres despite renewables strategy Nov 12 Ontario Securities Commission finds most registered firms early in AI adoption Nov 12 France to open international defence AI centre in Rennes in July 2027More from Data Centers
Nov 13 National Stock Exchange of India adds liquid cooling to expand AI computing Nov 13 Luxembourg startup OwlO Cloud plans orbital data centers by 2030 Nov 13 Polar DC adds Palistar financing as 2026 commitments pass EUR 1 billion Nov 13 Fermi lands 600MW hyperscaler power deal as TensorWave lease is cancelled Nov 13 SEMIFIVE's custom AI chip orders jump 437% to a record quarterAI Policy Brief
Weekly report on AI regulations, safety standards, government policies, and compliance requirements worldwide.
Whitepaper
Tensordyne Napier: What If One Rack Could Do the Work of Nine?
Tensordyne
This Tensordyne whitepaper presents Napier, an inference-focused AI processor and rack-scale system based on the company’s TDN Math logarithmic number system. It examines infrastructure requirements for large mixture-of-experts and agentic models, compares major inference architecture approaches, and details the TDN AIP processor, TDN72 pod, TDN Link fabric, and Napier Ultra configuration. The paper reports simulation-based performance, cost, and accuracy-validation results, including Tensordyne’s projected comparison of one Napier rack with a nine-rack Nvidia Rubin plus Groq deployment; the chip is reported as taped out and in fabrication.
Read moreYou may also like
UK AI data centres could emit 4.1 million tonnes of CO2 a year
Energy North drops 2028 start date for 1 GW outback data centre after regulator pause
Spain Eases Proposed Rules for Data Centers
US Data Center Power Demand Grows 10 Times Faster Than Grid Capacity
Portugal Plans Renewable Power and Water Rules for Data Centers
Daily AI Brief: the AI news that matters, in your inbox.