Crusoe Ends $1.25 Billion Boom Turbine Deal
Crusoe ended its $1.25 billion agreement to buy 29 Superpower turbines from Boom Supersonic, according to TechCrunch. Deliveries of the 42 megawatt natural gas turbines had been due to begin in 2027.
Boom CEO Blake Scholl said turbines are no longer part of Crusoe's near term primary power plans for its Abilene campus and other sites. Boom still expects to deliver about 250 megawatts of Superpower capacity to other customers in 2027 and plans to reach 1 gigawatt in 2028.
Crusoe's initial 1.2 gigawatt Abilene data center uses grid power, with a gas turbine plant serving as backup. A separate 900 megawatt Abilene data center under construction for Microsoft will use gas turbines located on site.
We hope you enjoyed this article
Consider subscribing to one of our newsletters like Silicon Brief or Daily AI Brief.
Also, consider following us on social media:
More from Data Centers
Nov 13 Northstar ramps up modular AI data center production, projects $450 million in revenue Nov 13 LCH2 gets $1 million more for Washington clean energy campus with AI computing site Nov 12 Fed economists find AI boosts data center investment but has little effect on jobs and productivity so far Nov 12 Report urges caution on space data centers: 10% of 2030 AI capacity in orbit would need 700 launches a year Nov 12 Congress leaders back tighter AI chip export curbs after Nvidia scandalSilicon Brief
Weekly coverage of AI hardware developments including chips, GPUs, cloud platforms, and data center technology.
Industry analysis
2025 Global Business Services Agenda: Gen AI Takes Center Stage
This industry analysis by The Hackett Group explores the transformative impact of generative artificial intelligence (Gen AI) on global business services (GBS) in 2025. The study highlights the shift from exploration to acceleration of Gen AI initiatives, with 89% of executives advancing these projects to improve customer satisfaction, innovate products, and reduce costs. The report also discusses the challenges and strategies for successful Gen AI adoption, emphasizing the need for a technology-enabled operating model and the importance of reskilling the workforce.
Read moreYou may also like
Anthropic buys 1.7 GW of gas-fired generator orders for $3.4 billion
Venture Global Signs Power Deals for Up to 10 GW of Compute Capacity
Hitachi Energy and Ansaldo Energia Partner on Data Center Power Systems
AEP, Amazon and X-energy Study 960 MW Indiana Nuclear Project
UK AI data centres could emit 4.1 million tonnes of CO2 a year
Daily AI Brief: the AI news that matters, in your inbox.