IREN details 900MW AI data centre campus near Wagga Wagga, grid capacity not yet secured
IREN has set out plans for Redbank, a proposed AI data centre campus near Wagga Wagga in regional New South Wales with up to 900MW of gross electrical capacity and about 600MW of IT load, W.Media reports. A scoping report for an IREN subsidiary proposes three new 330kV feeder bays at Transgrid's Wagga Wagga substation, about 2.5km away, and underground cables to a new on-site substation serving five data halls.
IREN says it will pay for the dedicated connection works, and connection planning with Transgrid has been under way since May 2026. But the report does not show a signed connection agreement or a formal allocation of transmission capacity, and Transgrid said it could not comment on individual applications. IREN has previously said Redbank is not part of its announced 5GW secured-power portfolio.
The 900MW figure is the campus's maximum gross electrical demand, not its expected average use.
We hope you enjoyed this article
Consider subscribing to one of our newsletters like Silicon Brief or Daily AI Brief.
Also, consider following us on social media:
More from Data Centers
Nov 23 MIT trains a small language model to design analog chips on a laptop Nov 23 MetaOptics secures up to S$32 million facility to fund US metalens fab Nov 22 Architect Labs says AI agents designed its Frostbite CPU end to end Nov 22 Nscale's $35 billion US IPO faces scrutiny over ByteDance ties Nov 22 ASIO chief warns data centres and AI expose Australia to foreign interferenceSilicon Brief
Weekly coverage of AI hardware developments including chips, GPUs, cloud platforms, and data center technology.
Industry analysis
2025 Global Business Services Agenda: Gen AI Takes Center Stage
This industry analysis by The Hackett Group explores the transformative impact of generative artificial intelligence (Gen AI) on global business services (GBS) in 2025. The study highlights the shift from exploration to acceleration of Gen AI initiatives, with 89% of executives advancing these projects to improve customer satisfaction, innovate products, and reduce costs. The report also discusses the challenges and strategies for successful Gen AI adoption, emphasizing the need for a technology-enabled operating model and the importance of reskilling the workforce.
Read moreYou may also like
Energy North drops 2028 start date for 1 GW outback data centre after regulator pause
South Australia backs gas power for AI data centres despite renewables strategy
Submissions close on 1 GW Project Meridien AI data centre
National Grid Plans Britain’s Biggest Substation Near Teesside AI Data Centre
Estonia receives data centre grid requests for 2,900 MW, nearly double its peak demand
Daily AI Brief: the AI news that matters, in your inbox.